Claims settled in 6 days instead of 21 We replaced Halden Versicherung's 2002 claims system one claim type at a time, with the old and the new system running side by side for ten months.
- Client
- Halden Versicherung
- Industry
- Insurance
- Duration
- 18 months
- Team
- 14 people
- Scope
- Legacy modernisation, Custom software, Data and AI, Backend and integrations, QA and test automation
- Technology
- Java, Spring Boot, Camunda, DMN, Kafka, Debezium, PostgreSQL, Oracle, Angular, OpenShift
Situation
Halden Versicherung AG is a property and casualty insurer, founded in Hamburg in 1898 as a mutual, with its head office in the City Nord district. It has about 1,100 employees and 1.2 million policies for household contents, residential buildings, private liability and bicycles, sells through agents and online, and handles about 140,000 claims a year. A Hamburg client we first worked for in 2016 recommended us. Claims ran on a system built in 2002 in Oracle Forms and PL/SQL. Successive teams had extended it for twenty years, and the people who built it had retired. Settling a claim took 21 days on average. Claims came in by letter and email, and handlers typed them in by hand. Every change to the system took months, and nobody could list all the rules it applied.
Challenge
Halden wanted claims settled faster and rules that its own people could read and change. Nobody could specify the old system completely, which ruled out a single cut-over. Claim types had to move to the new platform one at a time while the old system went on handling the rest, and the two had to stay consistent for as long as they ran in parallel. Changes to the old Oracle code took months, so the new platform had to read from the old database without touching the code. Automatic approval of small claims needed limits from the chief actuary and evidence to back them. BaFin's requirements for insurers' IT applied throughout, and the works council (Betriebsrat) had a say in any change to how work is assigned and monitored. Everything had to run in Halden's private cloud on OpenShift, and at the end Halden's own team of eight developers would take the platform over.
What we did
A strangler fig plan
We spent two weeks in Hamburg in April 2022, mapped the claims process and listed the 11 modules of the old system. In May we agreed a strangler fig plan. A routing layer in front of both systems decides, per claim type, which of them handles a claim. Debezium streams changes from the old Oracle database into Kafka, which keeps the two systems consistent, and the old code never had to change. The new services are Java 17 and Spring Boot, Camunda 8 runs the claim process in BPMN, and new data goes into PostgreSQL.
Intake that reads the documents
In June and July we built the new intake: an online claim form, and email intake that pulls the fields out of invoices, repair estimates and police reports. Extraction is OCR plus a field extraction model that our ML engineer trained on Halden documents, and it runs with the rest of the platform in the private OpenShift cloud. Handlers work in an Angular application, where an incoming document arrives with its fields already filled in for them to check.
140 rules nobody wrote down
The plan gave rule discovery six weeks; it took four months, from August to November. The rules sat in PL/SQL triggers, in Forms code and in the handlers' habits. We went through 2.3 million historical decisions in the logs, turned patterns into candidate rules and checked them in interviews (26 in total). Take HR-047: after a flood, every claim from a list of postcodes gets a site visit, and that list was a table one person updated by hand. Each of the 140 rules became a DMN table with examples and tests, signed off by the claims department.
First slice, then automatic approval
Because of the rules, the first slice went live in December 2022 instead of October: small household contents claims (Hausrat) moved to the new platform, and everything else stayed in the old system. Automatic approval ran in shadow mode from January. With the works council we agreed that the system assigns work but nobody gets an individual productivity dashboard, so statistics exist per claim type and never per person. After 8 weeks of shadow mode, in which the system agreed with the handlers in 97.4% of cases, automatic approval went live in March with a limit of €300.
Ten months in parallel, then handover
Liability (Haftpflicht) and buildings (Wohngebäude) moved between April and June 2023. In May, after 8 more weeks of data, the actuaries raised the automatic approval limit to €1,000. Later slices reused the rules from the first one, so the end date held despite the late start. Bicycles and recourse moved in July and August. On 29 September 2023, after ten months of parallel running, the old system stopped taking new claims and has been read-only since. Halden's own team of eight developers took over the platform, with us in support.
Results
- average time to settle a claim in Q1 2024, against 21 days in 2021
- 6 days
- of claims up to €1,000 settled with no human step (Q1 2024)
- 35%
- business rules documented and tested, with 1,900 test cases
- 140
- handler time spent typing in incoming documents, Q1 2024 against 2021
- −70%
For the first time my department can read the rules we settle claims by and change them ourselves. We switched off a system we had used since 2002 without a single weekend of panic.